UK-based engineering consultancy RVA Group has been appointed by Enemalta Corporation to help plan the decommissioning of the Marsa power station.

RVA announced that it has been contracted by Enemalta in its review and assessment of two existing power stations, Marsa and Delimara, as part of the company’s strategy to update its electricity generation technology.

The initial phase of work begins with the preparation of outline plant decommissioning and includes a monitoring programme and devising a waste management plan.

The Marsa power station is expected to be phased out by 2015 and so RVA team also has to develop a full decommissioning plan for the plant. Almost all electricity produced at Marsa is derived from the combustion of residual heavy fuel oil.

"As with any decommissioning project there are numerous factors to consider, which is why it is important to undertake extensive investigative work before a recommended plant decommissioning plan is prepared,” said RVA managing director Richard Vann.

“There can never be a ‘one size fits all’ approach. On this particular project we have to think about the removal and dismantling in the most cost-effective way of all mechanical and electrical equipment and the structures themselves. This client is keen to ensure best practice from day one, therefore it is crucial that every risk is assessed and every opportunity explored,” he said.

RVA’s plans – which are to be submitted to the Malta Environment & Planning Authority for approval – will detail how, in what sequence and over what period of time this project should be pursued. It will also include an estimate of the resources required, security protocols and the costs involved. The authorised plans will form the basis for decommissioning implementation.

Martin Attard-Montalto, division manager at Enemalta, said: “We know we are going to need additional generation capacity in the coming years, but we have recognised the need to replace some of our outdated technology with more efficient plant. This will not only ensure legislative compliance but will significantly reduce primary fuel consumption and subsequent emissions.

“We appointed RVA following a rigorous tendering process, on the basis of their specialist expertise and proven independent experience within the field of planning for power station decommissioning. It is important that Enemalta makes not only the safest, but also the most environmentally and commercially sound decisions going forward, so this guidance and much-needed insight will allow us to progress in this manner.”

avatar
Another commision to our English cousins. We have enough manpower to do it all minister. Stop wasting our money on foreigners which you are borrowing from the markets to service the debt that you are running up!
avatar
It grieves me, that with all these professors and euro engineers and other know alls, we still have to get foreigners to "decommission" something. Let alone "building" something. What is happening to this country? Telecommunications, airmalta, public lottery, bus service, airport, free port, ex sea malta, banks, etc, etc. All run by foreigners. Where is the local talent? If we are still inexperience, when are we going to be ready to take over the running of Malta. We have been independent since 1964 after all. One thing that I find strange is that we are incapable of running, amongst other things "il-lottu", yet our politicians have no qualms in running the country. Maybe we should get some consultants to run the country for a few years and see how it goes. We might like it.
avatar
Luke Camilleri
DECOMMISSIONING of the Marsa power station? . Does that means that the national Coffers willbe getting the €4,000,000 in commission paid to Mr. Joe Mizzi BWSC agent????????