Enemalta paid BWSC €8 million extra for Delimara services never carried out

Energy minister reveals that Enemalta never pursued €4 million claim against BWSC for turbine damage because legal consultants felt legal grounds were too weak.

€16 million more expensive than BWSC originally charged Enemalta for - the increased price was later halved.
€16 million more expensive than BWSC originally charged Enemalta for - the increased price was later halved.

Enemalta paid Danish contractors BWSC an extra €8 million over and above its originally stated contract price for the Delimara power station extension, without ever verifying why the company was raising its price after it had been successfully selected for the installation of its turbines.

In a ministerial statement, energy minister Konrad Mizzi today revealed in parliament that BWSC had raised its original bid of €147 million to €164.9 million during tendering, to include strategic spares and a higher chimney.

However, Mizzi claimed, BWSC's additional €17 million failed to raise any protest from Enemalta as to why these additional items were not included in its original bid.

"Given that BWSC had already been officially selected as the winner of the tender, an agreement was carried out to halve the items added on by BWSC, namely amounting to €3 million for the chimney height and €5 million for strategic spares, which meant a final increased price of €8 million on the original BWSC bid," Mizzi declared.

"BWSC managed to charge Enemalta €8 million more for items that were not included in the original contract, and which were not even carried out."

Mizzi also said that the €5 million in strategic spares were hived off under the five-year maintenance and spare parts agreement, which however was not signed with BWSC. As for the €3 million paid to increase the 65-metre chimney to a height of 100 metres, Enemalta never claimed back this expense which it had paid for, when the work itself was not even carried out.

And yet, Enemalta still forked out an additional €1 million for the purchase of the strategic spares which were not provided by BWSC in the first place.

Mizzi also revealed that the Delimara contract gave the Danish firm a letter of credit of €16.5 million, according it the right to withdraw this money from the bank if it was not paid what it was owed by Enemalta. "It's an anomaly that a state corporation issues such a letter of credit, when BWSC's own guarantee in favour of Enemalta was of just €8.25 million," Mizzi said.

Mizzi also put paid to claims by former prime minister Lawrence Gonzi that BWSC had accepted to pay back any losses incurred in the repair of the damaged steam turbines that occurred during the testing phase for Delimara's extension in October 2012.

"Not only did this not take place. But it was BWSC that was claiming €13 million from Enemalta due to delays in issuing permits from the Malta Environment and Planning Authority, as well interest on late payments. Additionally there was €2.6 million paid for a warranty to be extended to December 2013," Mizzi said.

The minister added that an alleged claim €4 million Enemalta was preparing to make against BWSC was never even submitted, because there were no legal basis for it. "Enemalta's own legal consultants advised against it and no claim against BWSC ever took place. The consultants also advised against a claim of €8 million for liquidated damages and €700,000 for the purchase of chemicals, feeling the legal grounds were weak."

The reason for the lack of legal grounds resulted in the fact that Enemalta still had effective control of eight functioning machines, while the damage resulted in two turbines.

"It meant that the €8 million in damages that ensued - specifically calculated on a contractual agreement to pay Enemalta 1% of the contract value for every week that a delay occurs - were neutralised for the fact that it was only one steam turbine that was not working."

As it turns out however, Enemalta could not even seek for legal redress in Maltese courts because it was contractually bound to seek arbitrage in the London Arbitration Centre of the International Chamber of Commerce. "Today we know that BWSC was in a position of claiming far more money had Enemalta pursued its claim."

Mizzi announced in parliament that both Enemalta and BWSC would cease making legal claims that were planned to take place against each other, over damages incurred in the testing phase of the steam turbines and delays in the issuing of permits to BWSC, because of the expense involved in pursuing these claims.

"After having held discussions with both sides, BWSC has ceded its claims against Enemalta's late payment and accepted to pay a €700,000 claim."

avatar
x'hadma hdimtuh lil poplu Malti GONZIPN. Nispera li xi darba thalsu ta ghemilkhom. On a silver platter, ghax kontu tafu li jekk tridu dawn il flus lura trid tmorru quddiem qorti ingliza. U ara xi spjess. Veru hadma bizilla. You should be ashmed of yourselves all of you.
avatar
x'hadma hdimtuh lil poplu Malti GONZIPN. Nispera li xi darba thalsu ta ghemilkhom. On a silver platter, ghax kontu tafu li jekk tridu dawn il flus lura trid tmorru quddiem qorti ingliza. U ara xi spjess. Veru hadma bizilla. You should be ashmed of yourselves all of you.
avatar
Priscilla Darmenia
Call it what you want – incompetence; ignorance; mismanagement; abuse of public funds and the list goes on. But in the end who is going to be held responsible for the THEFT of such funds from the public kitty? The best profession in Malta is to be a politician. Politicians lie; misinform; do not keep promises; squander public funds; pay themselves behind the public’s back; abuse of their power and position and the list goes on, but they never pay a cent or go to jail for their actions.
avatar
TONIO FENECH, WHO WAS RESPONSIBLE FOR ENEMALTA, AND WHO DECLARED THAT THE BWSC CONTRACT WAS IN HAND, MUST BE HELD ACCOUNTABLE AND CRIMINAL ACTION TAKEN AGAINST HIM AND GONZI FOR LYING TO THE PEOPLE, MISLEADING THEM AND DENYING THEM TO THE PEOPLE WHO WERE MADE TO PAY THROUGH THEIR TEETH FOR ENERGY BILLS. THIS PRESENT GOVERNMENT WOULD BE CONSIDERED IN COLLUSION IF THEY DO NOT TAKE SUCH ACTION.
avatar
min ha xi rigal ta zewgt liri Maltin spicca interdetjat, u min fotta dawn il-flus fejn sejjer? Qed nistenna tibda issir Gustizzja mhux mazz-zghir biss imam mal-KBIR ukoll. Min huwa hati gahndu jiehu dak li haqqu.
avatar
Rita Pizzuto
Shame on you GonziPN! Isn't this corruption?
avatar
€8 million .... How much is € 8 million? Practically twice as much as paid in COMMISSIONS to BWSC Agent for looking up contractors in the Yellow Pages! How much is € 8 million? Three times as much as collected by Strina in a year ( €2.3 million collected last year )! How much is € 8 million? A LOT , A WHOLE LOT!
avatar
€8 million .... How much is € 8 million? Practically twice as much as paid in COMMISSIONS to BWSC Agent for looking up contractors in the Yellow Pages! How much is € 8 million? Three times as much as collected by Strina in a year ( €2.3 million collected last year )! How much is € 8 million? A LOT , A WHOLE LOT!
avatar
€8 million .... How much is € 8 million? Practically twice as much as paid in COMMISSIONS to BWSC Agent for looking up contractors in the Yellow Pages! How much is € 8 million? T
avatar
Fuq dawn il- hnizrijiet kemm messa tikteb is-sahhara- l-isposkewomen ta SimonPN u mela minn hemm fuq l- Boards, li fi zmien GonziPN kienu jithabbru biss fil-Gazzetta tal-Gvern u mohbija hemm!